HighWater Utilities

Water Filtration Plant Filter and SCADA Improvements

The council was scheduled to consider a $7.77 million contract with Gallo Construction Corp. to upgrade filters and the SCADA control system at the city's water filtration plant. It's one of the largest infrastructure investments on the agenda and affects the reliability of the city's drinking water.

3 mentions (2 this month)Last discussed Oct 26, 2026
HighWater Utilities

Emergency sewer repairs on Broad Street

A $485,000 transfer within the sewer fund would pay for emergency sewer repairs on Broad Street.

1 mentionLast discussed Sep 24, 2026
HighWater Utilities

Water department staffing and rate stability

Veteran water staff with 87 combined years are retiring, and Vradenburgh wants long-overdue pay upgrades for positions untouched in 30 years. Big equipment purchases may go into a bond paid through facility fees instead of water rates, keeping user rates flat.

1 mentionLast discussed Sep 23, 2026
HighWater Utilities

PFOS and Catskill Aqueduct water reimbursement amendments

Amendments to two state DEC contracts that reimburse Newburgh for water purchased from the Catskill Aqueduct and for extra costs of providing alternative drinking water amid PFOS contamination.

3 mentionsLast discussed Sep 22, 2026
HighWater Utilities

Lead Service Line Replacement Funding

The council was to consider backing a state bill that funds replacing lead water service lines. Support could help Newburgh compete for pipe-replacement dollars.

3 mentionsLast discussed Jul 13, 2026
HighWater Utilities

South Interceptor Sewer Improvements

The council was scheduled to consider three state grant applications totaling up to more than $18 million for major sewer work — the South Interceptor Phase V and West Trunk Sewer Contract No. 3. These are core pieces of the city's long-term sewer control plan.

2 mentionsLast discussed Jul 13, 2026
HighWater Utilities

West Trunk Sewer Rehabilitation Contract No. 3

Another sewer grant application — up to $4.4 million with a 25% match — to design and rebuild the West Trunk Sewer. Aging sewer infrastructure means expensive failures if it's not addressed.

2 mentionsLast discussed Jul 13, 2026
HighWater Utilities

Long Term Control Plan Sewer Contracts

Three ARCADIS contracts totaling about $2.18 million were slated for discussion — South Interceptor ($496,300), West Trunk Sewer ($712,900), and Liberty Street sewer separation ($974,900). These design contracts advance the city's multi-year effort to cut sewer overflows into the Hudson.

2 mentionsLast discussed May 21, 2026
HighWater Utilities

Washington Lake Dam Engineering Assessment

The council was set to discuss a $25,000 engineering assessment of the Washington Lake Dam — the reservoir serving Newburgh's water supply. Knowing the dam's condition matters for water safety and future repair budgeting.